Shobad Power Plant’s Unit One Major Overhaul was Successfully Completed
The Shobad combined cycle power plant’s unit One overhaul (HGPI) was successfully completed.
The project which began with 30 day forecast and started on October 13, 2018, was completed by the team’s effort in 18 days and on October 30, 2018 and the unit number One was synchronized with a national grid.