MahTaab Group intends to build a new petrochemical complex in the Parsian Energy Intensive Industrial Special Economic Zone (PEISEZ) with the aim of producing propylene and downstream derivatives from the propane feedstock.
“MahTaab Petrochemical Development” company, which is a subsidiary of MahTaab Group, was established for developing that petrochemical project. The company has obtained the agreement in place from the Ministry of Petroleum (MOP) for developing and building a PDH+ plant in 2021, and the long-term contract for receiving 180 KTA propane feedstock has been signed with the National Iranian Gas Company (NIGC) in 2023.

The project development phase has been started from 2024 and according to the project timeline, the construction of the complex will be started in 2026 and completed in 42 months.

Project development phase activities:

  • Engineering

    • Conceptual design
    • Licensor selection
    • Process design package preparation
    • Basic design
    • FEED
  • Land Preparation

    • Geotechnical studies
    • Fencing
    • Soil improvement execution
  • Securing finance

  • Receiving other authorizations

Location

Parsian Energy Intensive Industrial Special Economic Zone, Asaluyeh, Bushehr, Iran On Map