Commencement of Nominal-Capacity Power Generation in the Rudshur Steam Unit
In the early hours of Tuesday, 26 August 2025, a significant milestone was achieved in the development of the Rudshur combined-cycle power plant. Foll...
In the early hours of Tuesday, 26 August 2025, a significant milestone was achieved in the development of the Rudshur combined-cycle power plant. Foll...
At 21:00 on Wednesday, 13 August 2025, the steam section of the Rudshur combined-cycle power plant was synchronized with the national electricity grid...
The steam turbine unit of the Rudshur Power Plant was successfully synchronized with Iran’s national power grid for the first time at 7:05 PM on Satur...
The Renewable Energy and Energy Efficiency Organization (SATBA) has issued a construction permit for a 12 MW solar power plant at the Shams Sarakhs Po...
As the warmer months approach and electricity demand continues to rise, the steam section project of the Rudshur Power Plant is progressing at an acce...
The expansion project of Mahtab Kish’s desalination plant commenced in May of last year. Today, with the commissioning of the new system and the addit...
The farewell ceremony for the former CEO and the introduction of the new CEO of MahTaab Group was held in the presence of the board of directors, seni...
In this documentary, we take you through the stages of constructing the Siahpoush Wind Power Plant from initial assessments and site selection to turb...